Santa Ana
City Council
11. Construction Contract with Hardy & Harper, Inc. for the Rehabilitation of Civic Center
Drive from Shelton Street to Flower Street Project (Project No. 256711) (General
Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an amendment to the Fiscal Year 20242025
Capital Improvement Program to include $500,000 in Civic Center Maintenance funds
for the Civic Center Rehabilitation from Shelton Street to Flower Street Project,
Project No. 256711.
2. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$1,144,000, which includes $915,000 for the construction contract, $137,000 for
contract administration, inspection, and testing, and a $92,000 project contingency for
unanticipated or unforeseen work due to the complexity and extensive scope of this
project.
3. Award a construction contract to Hardy & Harper, Inc., the lowest responsible
bidder, in accordance with the base bid in the amount of $915,000, subject to change
orders, for construction of the Civic Center Rehabilitation (Shelton Street to Flower
St.) Project (No. 256711), for a term beginning March 18, 2025 and authorize the
City Manager to execute the contract.
4. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption
Environmental Review No. ER2024114 was filled for Project No. 256711.