19. NOTICE OF COMPLETION: WATER MAIN REPLACEMENT PROJECT ON
MARENGO AVENUE – F2M24-34, C2M24-35, M2M25-38
On May 13, 2024, the City Council awarded a contract to CEM Construction Corp., for the
Water Main Replacement Project on Marengo Avenue in the amount of $659,105.00.
There were two authorized change orders during the project. The change orders were to
remove and replace 16-inch and 18-inch existing valves, abandoning additional water
main pipe, and various unforeseen miscellaneous items. The change order increased the
total amount of the contract by $150,527.43, for a total project cost of $809,632.43. The
project has been completed in accordance with the City’s requirements and specifications.
As such, it would be appropriate for the City Council to accept the project as complete and
instruct the City Clerk to file the Notice of Completion be filed with the County of Los
Angeles Recorder’s Office.
Recommended Action: City Council accept the work of CEM Construction Corp. for
the Water Main Replacement Project on Marengo Avenue as complete in the amount of
$809,632.43; direct the City Clerk to file a Notice of Completion with the County of Los
Angeles for recordation; direct the Finance Director to release the five percent retention
35 days from the date of recordation if no liens are filed; and, direct staff to undertake the
steps necessary to finalize Council’s action. (M2M25-38)