17. AWARD OF CONTRACT WITH TOTAL ENVIRONMENTAL MANAGEMENT, INC. FOR
EMERGENCY SERVICE – F2M25-6B, C2M25-9, M2M25-36
The chiller in the Police Department’s building has failed and is no longer operational. As
a result, there is currently no cooling in the building. City staff entered into an agreement
with Total Environmental Management, Inc. (TEM) to provide a temporary cooling unit for
the building for a minimum of sixty days in the amount of $24,600.00. The replacement of
the chiller has been identified in Alhambra’s Facility Assessment Report. In addition, staff
is working with a Heating, Ventilation, and Air Conditioning (HVAC) consultant to
determine other improvement recommendations. Staff has learned from some
manufacturers that it could take about a year to procure the equipment. Staff is requesting
the City Council approve extending the agreement with TEM for another 12 months, for
an additional amount of $147,600.00.
Recommended Action: City Council authorize an agreement, subject to final
language approval by the City Manager and City Attorney, with Total Environmental
Management, Inc. for emergency service to provide a temporary cooling unit at the
Alhambra Police Department at a cost not to exceed $12,300.00 per month, or
$147,600.00 for 12 months if needed; and, direct staff to undertake the steps necessary