2. Potholing: Potholing was not included in the original project scope. Potholing performed during the design phase is an efficient method to determine where underground utility lines are located and mitigates delays and cost overruns during the construction phase. Identifying utility and other subsurface conflicts prior to construction also reduces the likelihood of costly repairs to utility lines and encountering safety hazards during construction. A pothole report will be prepared and made available to the construction contractor.