6M. ACCEPTANCE OF THE STANTON CITY HALL FIRE ALARM UPGRADE PROJECT
(TASK CODE NO. 2022-834) BY THE CITY COUNCIL OF THE CITY OF STANTON,
CALIFORNIA
The Stanton City Hall Fire Alarm Upgrade Project consisting of the design and upgrade
of the existing fire alarm system is now complete. The final construction cost for the
project was $182,376, the contract award amount. The City Engineer, in his judgment,
certifies that the work was satisfactorily completed as of April 15, 2025, and recommends
that the City Council accept the completed work performed on this project.
RECOMMENDED ACTION:
1. City Council declare this project categorically exempt under the California
Environmental Quality Act, Class 1, and 15301(a); and
2. Accept the completion of improvements for the Stanton City Hall Fire Alarm Upgrade
Project, as certified by the City Engineer, and affix the date of April 15, 2025, as the
date of completion of all work on this project; and
3. Approve the final construction contract amount of $182,376 with Climatec, LLC; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to
Climatec, LLC in the amount of $9,118.80.