Agenda Item
· Signal Hill
City Council — Item a
Original agenda text
Order of Business 12
a.
CIVIC CENTER MASTER PLAN AND SIGNAL HILL AMPHITHEATER
PROJECT UPDATE
Summary:
The 2023-2028 Strategic Plan identifies the development of the Civic Center
Master Plan (CCMP) as a key City objective. On August 27, 2024, the City
Council adopted the CCMP, which outlines a phased approach to redeveloping
the Civic Center campus. The plan designates three phases, with the building of
a new amphitheater as Phase One; replacement of the existing Community &
Youth Center and related amenities as Phase Two; and accessibility, park
connectivity, and landscape improvements, particularly those enhancing Signal
Hill Park and Jessie Nelson Circle, as Phase Three.
At this same meeting, the City Council directed staff to explore the feasibility of
advancing select elements of Phase Three to improve accessibility from existing
parking areas to Signal Hill Park and the new amphitheater and assess
opportunities for additional accessible parking and plaza design enhancements
along Jessie Nelson Circle. In May 2025, staff met with individual City Council
members to review the updated amphitheater design and to discuss the
evolution of the process which accounted for input through community outreach,
presentations to City committees, commissions, the City Council, and expert
guidance from the industry consultants. The updated design includes a modified
scope that accounts for current and future programming needs and is
appropriately scaled for the proposed use and maximizes its functional utility
over time.
Staff worked with John Kaliski Architects, Incorporated (JKA) to explore the
modified Phase Three accessibility Improvements that could enhance
pedestrian accessibility and additional accessible parking. Given the topography
of Signal Hill Park, especially the elevation changes from the park to Jessie
Nelson Circle, incorporating accessibility improvements from the City’s parking
lots to the amphitheater requires a significant amount of grading and
improvement work. While these preliminary design efforts were helpful to
provide structure and scope for potential Phase Three improvements, staff
recommends focusing the use of the City’s funding on the amphitheater and
revisiting Phase Three at a later date. As a follow-up to the City Council
direction, this report provides a status update on the Phase One amphitheater
design and provides an update on specific Phase Three elements and
improvements consistent with City Council’s request.
Strategic Plan Goal(s):
Goal No. 1: Financial Stability: Ensure the City’s long-term financial stability
and resilience.
Goal No. 4: Infrastructure: Maintain and improve the City’s
infrastructure, water system, and recreational spaces.
physical
Goal No. 5: High-Functioning Government: Strengthen internal communication,
recruitment, retention, systems, and processes to increase the
effectiveness and efficiency of City services.
Recommendation:
Provide direction to advance Phase One of the Civic Center Master Plan and
receive and file status update report.