Agenda Item
· Bell Gardens
City Council — Item 10
Original agenda text
Order of Business 10
10.10
Consideration of Award of Construction Contract for the
Various Residential Street Improvement Project (CIP No.
3940)
RECOMMENDATION: It is staff’s recommendation that the City
Council:
1. Award a Construction Contract to Hardy & Harper, Inc. in the
amount of $1,560,752.00 for the Various Residential Street
Improvements, FY 2024/2025 (CIP No. 3940);
2. Authorize the City Manager to execute the Construction
Contract and approve change orders that may be necessary
during construction to cover any unforeseen condition in an
amount not to exceed 10% of the construction contract; and
3. Appropriate an additional $200,000 in Measure M funds,
$303,000 in Measure R funds, and $250,000 in Prop C funds to
cover all construction and project management costs,
including contingency.
CONCLUSION: If the Construction Contract is awarded, staff will
process the contract for signatures and coordinate a pre-construction
meeting.
FISCAL IMPACT: The total estimated construction cost for the base
bid and additive bid is $1,560,752, with a 10% contingency for any
unforeseen conditions. The total estimated Project cost, including
design, construction, and construction management and inspection
is $1,998,168. The City’s FY 24-25 capital improvement budget
includes a total budget of $1,245,168 for the Project, consisting of
$672,735 in Measure R and $572,433 in Measure M local return funds.
Therefore, an additional appropriation of $200,000 in Measure M
funds, $303,000 in Measure R funds, and $250,000 in Prop C funds is
recommended to cover the $753,000 shortfall.
ATTACHMENTS:
Exhibit 1 - Construction Contract