Agenda Item
· Los Angeles
PLUM — Item 8
Original agenda text
Item
(8)
24-0976-S1
CD 14
Sustainable Communities Environmental Assessment (SCEA), Mitigation
Monitoring and Reporting Program and related Environmental findings; and a
report from the Los Angeles City Planning Commission relative to a Transfer of
Floor Area Rights (TFAR) of up to 274,795 square feet of floor area from the
Los Angeles Convention Center (Donor Site), located at 1201 South Figueroa
Street, to the Project Site (Receiver Site), thereby permitting a maximum 9.13:1
Floor Area Ratio (FAR) in lieu of the otherwise permitted 6:1 FAR; the TFAR
Transfer Payment in the amount of $1,373,975, pursuant to Section 14.5.10 of
Chapter 1 of the Los Angeles Municipal Code (LAMC), and Public Benefits
Payment in the amount of $11,462,471.39, pursuant to Sections 14.5.9 and
14.5.6B of Chapter 1 of the LAMC; and request to the Chief Legislative Analyst
to convene the Public Benefit Trust Fund Committee within six months of the
receipt of the Public Benefits Payment by the Public Benefit Trust Fund,
pursuant to Section 14.5.12 of Chapter 1 of the LAMC; for the demolition of
existing surface parking lot and the construction, use, and maintenance of a
51-story mixed use development comprised of 536 residential dwelling units
and up to 4,178 square feet of ground floor commercial uses on a 36,120
square foot lot area pre-dedication and 35,734 square feet of lot area postdedication. The Project would provide 581 automobile parking spaces for
residential use in six subterranean levels and three above-grade levels. The
building would have a maximum height of 603 feet, a floor area ratio of 9.13:1
(491,515 square feet), the removal of one street tree on Olive Street and
replacement with six new London plane trees; the removal of two street trees
on 11th Street and replacement with two Chinese flame trees; and would
require the export of approximately 118,543 cubic yards of soil; for the property
located at 1105 – 1123 South Olive Street; subject to revised Conditions of
Approval; and adoption of revised project findings. (The SCEA, No. ENV-20182601-SCEA was considered and adopted by the City Council on
December 11, 2024) [On May 13, 2025, the Planning and Land Use
Management (PLUM) Committee recommended a modification to
Condition No. 2.c.i.1 and Finding No. 1.c., to redirect 50 percent
($5,731,235.70) of the Public Benefit Payment, as the direct provision
payment to the Convention Center Expansion and Modernization project,
and referred the matter for City Council consideration. Thereafter, on May
27, 2025, the City Council did not take action, and referred the matter to
the PLUM Committee for further consideration.]
Applicant: Kevin Lindquist, MREG 1105 Olive, LLC
Representative: Paul Garry, Psomas
Case No. CPC-2018-2600-ZV-TDR-DD-SPR-MCUP
Environmental No. ENV-2018-2601-SCEA
Related Case No. VTT-82109
Fiscal Impact Statement: Yes