Agenda Item
· Signal Hill
City Council — Item b
Original agenda text
Order of Business 11
b.
July 8, 2025
PUBLIC WORKS CONTRACT WITH KORMEX CONSTRUCTION, INC. FOR
THE WILLOW MEDIAN IMPROVEMENTS PROJECT
Summary:
The 2023-2028 Strategic Plan for the City of Signal Hill prioritizes the completion
of the Citywide Median Project to enhance the aesthetics of the City’s major
arterial roadways. On January 10, 2023, the City Council approved a design
services agreement with SWA Group (SWA) to prepare landscape and irrigation
plans for all traffic medians citywide. SWA completed the design plans in
December 2024, providing updated landscaping and irrigation concepts for
implementation throughout the City. The plans are organized by individual
medians to support phased funding and construction, with a focus on prioritizing
medians along major arterial corridors and those in greatest need of
improvement. Among the plans identified the medians on Willow Street as a
high-priority area for enhancement.
Following a comprehensive and competitive bidding process, staff recommends
that the City Council award a contract to Kormex Construction, Inc., the lowest
responsive bidder, for a term of 90 calendar days and a not-to-exceed budget of
$478,156.50. Staff further recommends that the City Council authorize the City
Manager to execute a Public Works Contract with Kormex Construction, Inc. and
authorize the City Manager to execute the Member Agency Administered
Program Reimbursement Agreement to accept a $70,000 grant to be utilized
toward the project. If approved by the City Council, the construction of the
Willow Median Improvements Project would start in July 2025, with completion
anticipated by October 2025.
Strategic Plan Goal(s):
Goal No. 4
Infrastructure: Maintain and improve the City’s physical
infrastructure, water system, and recreational spaces.
Goal No. 5
High-Functioning Government: Strengthen internal
communications, recruitment, retention, systems, and processes to
increase the effectiveness and efficiency of City services.
Recommendations:
1. Authorize the City Manager to enter into a Public Works Contract with
Kormex Construction, Inc. for the construction of the Willow Median
Improvements Project for a term of 90 calendar days and a not-to-exceed
contract amount of $478,156.50, in a form approved by the City Attorney.
2. Authorize a contingency of $47,815.65 and up to a 30-calendar day
extension to accommodate additional scope of work and changes or
unforeseen conditions, to be utilized if approved by the Public Works
Director, for a total construction budget of $525,972.15.
July 8, 2025
3. Authorize the City Manager to execute the Member Agency Administered
Program (MAAP) Reimbursement Agreement in a form approved by the City
Attorney.
4. Adopt a Resolution appropriating $290,972.15, with $70,000 from MAAP
funds and $220,972.15 from the Capital Improvement Project reserve, to fully
fund the Willow Median Improvements Project, entitled:
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SIGNAL HILL,
CALIFORNIA, AMENDING THE ADOPTED BUDGET AND AUTHORIZING
BUDGET APPROPRIATIONS FOR FISCAL YEAR 2025-26.