Rosemead
City Council
E.
Accept Completed Improvements and Authorize Filing of a Notice of
Completion for City Project No. 31031 - Roof Replacement at Public Works
Office & Warehouse Building On January 14, 2025, the City Council
awarded a construction contract to Best Contracting Services, Inc. for the
Roof Replacement project at the City Public Services building. The total
construction budget, including a 10% contingency, was set at $537,267.50.
The completed improvements included replacing the deteriorating roof
with a new metal roof system, removing the existing hazardous roofing
materials, and weatherproofing the new roof. Furthermore, the scope of
work expanded to include the replacement of three non-functioning
swamp coolers with new systems, including the fabrication of metal curbs
to ensure a watertight system with all metal flashings.
Recommendation: That the City Council take the following actions:
1.
Accept the project completion for the Public Services Office and
Warehouse Building Project No. 31031 as performed by Best
Contracting Services, Inc. with the final contract amount of
$528,081.43; and
2.
Authorize the recordation of Notice of Completion with the Los
Angeles County Recorder and the release of retention funds 35 days
thereafter.
Staff Report