17. Amendment to the BristolTolliver Street Urban Greening Project Cost Analysis to add
$115,000 in Residential Development District 4 Acquisition and Development
funds and $176,000 in Community Development Block Grant Funds for a New Total
Construction Delivery Cost of $4,872,808 and Change Order to add $115,000 to an
Existing Construction Contract with Legion Contractors, Inc., for the Construction of
the Basketball Court at the Project (Project No. 246600) (NonGeneral Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an amendment to the BristolTolliver Street
Urban Greening Project Cost Analysis to add $115,000 in Residential Development
District 4 Acquisition and Development funds, and $176,000 in Community
Development Block Grant funds for a new total construction delivery cost of
$4,872,808.
2. Approve a Change Order to add $115,000 to an existing construction contract with
Legion Contractors, Inc., for the construction of the basketball court at the Bristol
Tolliver Street Urban Greening Project.