17. Amendment to the Bristol­Tolliver Street Urban Greening Project Cost Analysis to add $115,000 in Residential Development District 4 ­ Acquisition and Development funds and $176,000 in Community Development Block Grant Funds for a New Total Construction Delivery Cost of $4,872,808 and Change Order to add $115,000 to an Existing Construction Contract with Legion Contractors, Inc., for the Construction of the Basketball Court at the Project (Project No. 24­6600) (Non­General Fund) Department(s): Public Works Agency Recommended Action: 1. Approve an amendment to the Bristol­Tolliver Street Urban Greening Project Cost Analysis to add $115,000 in Residential Development District 4 ­ Acquisition and Development funds, and $176,000 in Community Development Block Grant funds for a new total construction delivery cost of $4,872,808. 2. Approve a Change Order to add $115,000 to an existing construction contract with Legion Contractors, Inc., for the construction of the basketball court at the Bristol­ Tolliver Street Urban Greening Project.