Agenda Item
· Bell Gardens
City Council — Item 2
Original agenda text
Order of Business 12
12.2
September 2025 Update on the John Anson Ford Park
Regional Aquatics Center Improvements Project
RECOMMENDATION: It is staff's recommendation that the City
Council receive and file the September 2025 John Anson Ford Park
Regional Aquatics Center Improvements update report.
CONCLUSION: After approximately 18 months of construction, the
completion of the John Anson Ford Park Regional Aquatics Center is
quickly approaching with final project completion projected to be
October 10, 2025. Staff are finalizing programming details and
operating hours in preparation of the opening of the new facility.
FISCAL IMPACT: The Project budget is $31,270,000, consisting of the
following funds:
Land and Water Conservation Fund - $6 million (Federal)
Supervisor Janice Hahn - $4 million (County)
Assemblymember Cristina Garcia - $2 million (State)
Congresswoman Roybal-Allard - $1.5 million (Federal)
General Fund - $14.6 million (City)
The current estimated total Project costs are as follows:
Design (RJM Design Group)
$1,045,100
Labor Compliance (Michael Baker International)
Construction
(Ardurra)
Management & Inspection
$224,200
$2,040,400
Construction Cost (Bernards)
$26,334,000
Construction Change Orders to Date (Bernards)
$1,104,600
Remaining Construction Contingency
Publication & Misc. Costs
TOTAL ESTIMATED PROJECT COST
$458,400
$1,200
$31,270,000
Annual staffing and operating costs of approximately $2,700,000 are
included in the Fiscal Year 2025-26 annual budget.
ATTACHMENTS: None