21. Award a Construction Contract to Optima RPM, Inc. for the Santa Ana Zoo Education
Hub Building A – Phase 1 Project (No. 232601) ( NonGeneral Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an appropriation adjustment recognizing
$166,000 in donations from Friends of Santa Ana Zoo into the PRCSA Fees &
Donations (0221300257081) revenue account and appropriate the same amount
into the PRCSA Fees & Donations (0221320066200) building expenditure account
for the Santa Ana Zoo Education Hub Building A – Phase 1. (Requires five
affirmative votes)
2. Approve an appropriation adjustment recognizing $750,000 in revenue collected in
prior years into the Acquisition & DevelopmentDistrict 3 (3131300250001) revenue
account and appropriate the same amount into the Acquisition & Development
District 3 (3131326066200) building expenditure account for the Santa Ana Zoo
Education Hub Building A – Phase 1. (Requires five affirmative votes)
3. Approve an amendment to the Fiscal Year 20252026 Capital Improvement
Program to include an additional $916,000 in construction funds for the Santa Ana
Zoo Education Hub Building A – Phase 1 Project (No. 232601).
4. Approve the Project Cost Analysis for a total estimated construction delivery cost of
9/16/2025
$4,454,082, which includes $3,563,265
for
contract administration, inspection, and testing, and $356,327 for unanticipated or
unforeseen work.
3. Approve an amendment to the Fiscal Year 20252026 Capital Improvement
Program to include an additional $916,000 in construction funds for the Santa Ana
Zoo Education Hub Building A – Phase 1 Project (No. 232601).
4. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$4,454,082, which includes $3,563,265 for the construction contract, $534,490 for
contract administration, inspection, and testing, and $356,327 for unanticipated or
unforeseen work.
5. Award a construction contract to Optima RPM, Inc., the lowest responsible bidder,
in accordance with the base bid in the amount of $3,563,265, subject to change
orders, for construction of the Santa Ana Zoo Education Hub Building A – Phase 1
Project (No. 232601), for a term beginning September 16, 2025 and ending upon
project completion, and authorize the City Manager to execute the contract.
6. Approve an Agreement with Berg & Associates, Inc., for Construction Management
and Inspection services for the Santa Ana Zoo Education Hub Building A – Phase 1
Project, in an amount not to exceed $374,315 for a threeyear term beginning
September 16, 2025 and expiring September 15, 2028, with an option for two, one
year extensions (Agreement No. A2025XXX).
7. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption
Environmental Review No. ER202562 will be filed for Project No. 232601.