San Clemente
City Council
11G. NOTICE OF COMPLETION - FY 2025 MAJOR STREET MAINTENANCE, CIP
PROJECT NO. 25303
Staff Recommendation
Adopt Resolution No. 25-154, which will:
1. Accept the FY 2025 Major Street Maintenance, CIP Project No. 25303,
from the contractor, Roy Allan Slurry Seal, Inc.
2. Authorize the City Clerk to execute and record the Notice of Completion
for the FY 2025 Major Street Maintenance.
3. Authorize the City Clerk to release the payment bond 35 days from the
recordation of the Notice of Completion upon verification with the
Engineering Division that no liens have been levied against the contractor,
Roy Allan Slurry Seal, Inc.
4. Authorize the City Clerk to release the performance bond for this project
upon receipt of a warranty bond in a form acceptable to the Public Works
Director/City Engineer in the amount of 25% of the total construction cost.