Huntington Beach
City Council
9.
25-803
Accept the lowest responsive and responsible bid and authorize
execution of a construction contract with KASA Construction, Inc. in
the amount of $453,066.00 for the Schroeder Park Improvements,
CC-1656, and authorize a 15% contingency
Recommended Action:
A) Accept the lowest responsive and responsible bid submitted by KASA Construction,
Inc. in the amount of $393,970 .00; and,
B) Reject bids 1 - 8 and 11 - 13, which were either withdrawn or deemed non-responsive;
October 21, 2025
and,
C) Authorize the Director of Public Works to approve change orders up to a 15%
contingency; and
D) Authorize the Mayor and City Clerk to execute a construction contract with KASA
Construction, Inc. in a form approved by the City Attorney.