Agenda Item
· Los Angeles
City Council — Item 20
Original agenda text
Item
(20)
13-0332
CD 15
CATEGORICAL EXEMPTION and TRADE, TRAVEL AND TOURISM
COMMITTEE REPORT relative to he Fourth Amendment to Permit No.
708 with Kinder Morgan Tank Storage Terminals, LLC, to allow
continued operation of the marine oil terminal at Berths 118-119 in the
Port of Los Angeles (POLA).
Recommendations for Council action:
1. CONCUR with the determination by the Board of Harbor
Commissioners (BOHC) that this action is categorically exempt
from the California Environmental Quality Act (CEQA) pursuant
to Article III, Class 1(14) of the Los Angeles City CEQA
Guidelines.
2. APPROVE BOHC Resolution No. 25-10578 authorizing
approval of the proposed Fourth Amendment to Permit No. 708
with Kinder Morgan Tank Storage Terminals, LLC to:
a. Retroactively extend the contract term by an additional
five years from April 14, 2025 through April 13, 2030, for a
total aggregate term of 42 years.
b. Continue operations of the existing marine oil terminal at
Berths 118-119 in the POLA through no later than April 13,
2029 and restore and surrender the site to the POLA no
later than April 13, 2030.
c. The annual base land rental rate of $2,255,182.88
remains unchanged, still subject to annual changes in the
Consumer Price Index and the next five-year
compensation reset scheduled for April 14, 2028.
3. AUTHORIZE the Executive Director, POLA, or designee, to
execute the proposed Amendment, already approved as to form
by the City Attorney, and return the Resolution to the POLA for
further processing, including Council consideration.
Fiscal Impact Statement: The City Administrative Officer (CAO)
reports that there is no impact on the City’s General Fund. Approval of
the proposed Fourth Amendment to Permit No. 708 with Kinder
Morgan will not change the annual base land rent of $2,255,182.88
but it is subject to annual changes in the CPI, and the next five-year
compensation reset scheduled for April 14, 2028. It is estimated that
continued operations under the proposed five-year term extension will
generate $3.1 million annually, or $15.5 million over the five-year
period for the POLA. Revenues will be deposited in the Harbor
Revenue Fund. The recommendations in the CAO report and
proposed actions comply with the POLA’s Financial Policies.