Item 100:
Hotel Circle and Taylor St Roundabout Improvement.
Total Estimated Cost of Proposed Action and Funding Source:
The total project cost in the Grant Application is $218,000. There is a 10% match
requirement of the grant application.
The grant funding from the State will provide $196,200. The City is responsible for the
remaining $21,800 (10%), of which $16,495.98 is from the ACTIVE TRANS IN LIEU
Fund, and $5,304.02 is from the CIP Streamview Drive Improvement Phase 2 project
fund.
Council District(s) Affected: 3.
Proposed Actions:
(R-2026-168)
Resolution authorizing the Mayor, or his designee, to make applications to Highway
Safety Improvements Program (HSIP) and take all necessary actions to secure funding in
an amount not-to-exceed $196,200 for the Hotel Circle Taylor Street Roundabout project;
and
Authorizing the Chief Financial Officer to increase the Fiscal Year 2026 CIP Budget, and
to accept, appropriate and expend an amount not-to-exceed $196,200, for the purpose of
preliminary engineering, designs, and construction of the project, contingent upon receipt
of a fully executed Grant Agreement if the Grant funding is secured, and related fiscal
actions.
Committee Actions Taken: N/A
Transportation Department: Steven Bliss, (760) 533-2904
City Attorney Contact: Ryan P. Gerrity