TUESDAY, NOVEMBER 4, 2025
South Whittier Community Bikeway Access Improvements Construction
Contract
Recommendation: Approve the South Whittier Community Bikeway Access
Improvements Project (Project), with an estimated construction contract amount
between $18,000,000 and $27,000,000 and a total project budget of
$31,900,000, and adopt plans and specifications for the Project. Funding for all
current fiscal year anticipated preliminary and construction engineering
expenditures for this project are available in the Road Fund (B03-Capital
Assets-Infrastructure and Services and Supplies), Public Works - Special Road
District 4 Fund (CP4-Services and Supplies), and the Fourth Supervisorial
District's Transportation Improvement Program in the Measure M Local Return
Fund (CN2-Capital Assets-Infrastructure and Services and Supplies) and
Proposition C Local Return Fund (CN9-Capital Assets-Infrastructure and
Services and Supplies) Fiscal Year 2025-26 Budget. Funding for future years
will be requested through the annual budget process. Advertise for bids when
ready. Find pursuant to California Public Contract Code, Section 3400 (c) (2),
that it is necessary to specify designated items by specific brand name in order
to match other products in use on a particular public improvement either
completed or in the course of completion. Find that the proposed actions are
not a project under the California Environmental Quality Act. Authorize the
Director of Public Works to take the following actions: (Department of Public
Works) ADOPT
Determine whether the bid of the apparent responsible contractor with
the lowest apparent responsive bid is, in fact, responsive and, if not
responsive, to determine which apparent responsible contractor
submitted the lowest responsive bid.
Award and execute a construction contract for the Project to the
responsible contractor with the lowest apparent responsive bid within or
less than the estimated cost range that exceeds the estimated cost range
by no more than 15%, if additional funds have been identified.
Extend the date and time for the receipt of bids, allow substitution of
subcontractors and relief of bidders, approve and execute change orders
within the same monetary limits delegated to the Director, accept the
Project upon its final completion, and make required findings and release
retention money withheld.
TUESDAY, NOVEMBER 4, 2025
Authorize the Acting Chief Executive Officer to modify Section 19.13.2 of the
Countywide Community Workforce Agreement by and between the County and
the Los Angeles/Orange Counties Building and Construction Trades Council
and the Signatory Craft Councils and Local Unions so that the section will not
apply to the Countywide Community Workforce Agreement projects funded by
Federal Highway Administration grant funds. (25-5680)