Agenda Item
· Los Angeles
LA County Board — Item 42
Original agenda text
Item
42.
Norwalk Boulevard-San Antonio Drive-Pioneer Boulevard Traffic Signal
Synchronization Program Beverly Boulevard to Carson Street
Construction Contract
Recommendation: Adopt a resolution finding that the modification and
synchronization of traffic signals in the Cities of Artesia, Cerritos, Hawaiian
Gardens, Lakewood, Long Beach, Norwalk, Santa Fe Springs, and Whittier and
in the Unincorporated Community of West Whitter/Los Nietos (4), is of general
County interest and that the County aid in the form of Highways-Through-Cities
funds in the amount of $2,961,500 shall be provided to the Cities of Artesia,
Cerritos, Hawaiian Gardens, Lakewood, Long Beach, Norwalk, Santa Fe
Springs, and Whittier to be expended in accordance with all applicable
provisions of law relating to funds derived from the Proposition C Discretionary
Grant Fund and Proposition C Local Return Fund. Approve the Norwalk
Boulevard-San Antonio Drive-Pioneer Boulevard Traffic Signal Synchronization
Program-Beverly Boulevard to Carson Street Project (Project) and adopt the
plans and specifications that are on file for the Project at an estimated
construction contract amount between $1,800,000 and $2,700,000. Advertise
for bids to be received before 11:00 a.m. on December 30, 2025. Find
pursuant to California Public Contract Code, Section 3400 (c) (2), that it is
necessary to specify the designated items by specific brand name in order to
match other products already in use on a particular public improvement either
completed or in the course of completion. Find that the proposed project is
exempt from the California Environmental Quality Act. Authorize the Director of
Public Works to take the following actions: (Department of Public Works)
ADOPT 4-VOTES
Execute funding cooperative agreements between the County and the
Cities of Artesia and Norwalk to allow the cities to contribute their share
of funding to the Project. The total Project amount is currently estimated
to be $4,037,000 with the City of Artesia’s share estimated to be
$928,300, the City of Cerritos’ share estimated to be $58,800, the City of
Hawaiian Gardens’ share estimated to be $2,500, the City of Lakewood’s
share estimated to be $95,400, the City of Long Beach’s share estimated
to be $800, the City of Norwalk’s share estimated to be $1,687,100, the
City of Santa Fe Spring’s share estimated to be $331,900, the City of
Whittier’s share estimated to be $433,400, and the County’s share
estimated to be $498,800. The Director may execute amendments to the
agreements to incorporate necessary programmatic and administrative
changes.
Determine whether the bid of the apparent responsible contractor with
the lowest apparent responsive bid is, in fact, responsive and, if not
responsive, to determine which apparent responsible contractor
submitted the lowest responsive bid.
Award and execute a construction contract for the Project to the
apparent responsible contractor with the lowest responsive bid within or
less than the estimated cost range of $1,800,000 and $2,700,000, or that
exceeds the estimated cost range by no more than 15%, if additional and
appropriate funds have been identified.
Extend the date and time for the receipt of bids, allow substitution of
subcontractors and relief of bidders, approve and execute change orders
within the same monetary limits delegated to the Director, accept the
Project upon its final completion, and release retention money withheld.
(25-6406)
Board Letter