17. APPROVE CHANGE ORDER: MAIN STREET AND FOURTH STREET SEWER MAIN
REPLACEMENT PROJECT - PHASE 2 - F2M22-53, C2M25-25, M2M26-10
On June 23, 2025, the City Council awarded a contract to Ramona Inc. for the Main Street
and Fourth Street Sewer Main Replacement Project - Phase 2 in an amount not to exceed
$2,941,665.50. The Project was originally proposed to provide slurry seal pavement on
Main Street from Fourth Street to Atlantic Boulevard. During the sewer construction, staff
and the contractor identified that the sub-surface of the street is deteriorated which was
not evident during the design phase. The additional work will provide structural strength,
ensures the roadway can withstand traffic loads, removes the deteriorated top layer and
any uneven patches from the sewer repairs. As part of this Change Order, damaged curb
and gutter and traffic loops will also be replaced.
Recommended Action: City Council approve Change Order No. 1 for the Main
Street and Fourth Street Sewer Main Replacement Project - Phase 2, increasing Contract
No. C2M25-25 with Ramona Inc. by $190,914.66 and bringing the total revised contract
value to an amount not to exceed $3,132,580.16; appropriate funds from the Measure R
fund in the amount of $190,914.66 to complete the project; and, direct staff to undertake
the steps necessary to finalize Council’s action. (M2M26-10)