Agenda Item
· Glendale
City Council — Item b
Original agenda text
Order of Business 4
b. Glendale Water and Power, re: Alternative Project Delivery Method for Engineering,
Procurement, and Construction of the Substation Battery, Charger and Rack
System Replacement Project
1. Resolution authorizing the General Manager of Glendale Water & Power, or his
designee, to issue a Request for Proposals (RFP) using the Engineering, Procurement,
and Construction Project Delivery Method for Substation Battery, Charger and Rack
System Replacement Project for
FY 2025-26, RFP No. 3998, and authorizing the City Clerk to solicit proposals