Hawthorne
City Council
17. Progress Payment #12 and Final Acceptance in the amount of $117,845.84 due to Klassic
Engineering & Construction, Inc of Orange, CA for Hawthorne Housing Rehabilitation of City
Owned Properties 2023 (Project #23-09).
RECOMMENDED MOTION:
Staff recommends that the City Council approve this Progress Payment #12 and Final Acceptance
and all recommend Change Orders #360 through #384 to Klassic Engineering & Construction Inc
of Orange, CA and release 5% retention amount 35 days after final payment has been approved.
CITY ATTORNEY'S CONSENT CALENDAR
(None at this time)