Agenda Item
· San Diego
City Council — Item 51
Original agenda text
Item
Item 51: Pure Water Phase 1 Consolidated Action - Contractor Contract Time Extensions.
Total Estimated Cost of Proposed Action and Funding Source:
These actions have no cost impacts as they are requesting authority for time extension
only.
Council District(s) Affected: Citywide.
Proposed Actions:
Subitem-A: (O-2026-84)
Introduction of an Ordinance authorizing the Mayor, or designee, to extend the
obligations of Construction Contract K-21-1848-DBB-3 with OHLA USA, Inc. for an
additional twelve months in connection with the Pure Water Phase 1 Morena Conveyance
North Project.
Subitem-A: 6 votes required pursuant to Charter Section 99.
Subitem-B: (O-2026-80)
Introduction of an Ordinance authorizing the Mayor, or designee, to extend the
obligations of Construction Contract K-21-1744-DBB-3-A with W.A. Rasic Construction,
Inc. for an additional thirty-two months in connection with the Pure Water Phase 1 North
City Pure Water Pipeline and Subaqueous Pipeline Project.
Subitem-B: 6 votes required pursuant to Charter Section 99.
Subitem-C: (O-2026-79)
Introduction of an Ordinance authorizing the Mayor, or designee, to extend the
obligations of Construction Contract K-21-1867-DBB-3 with PCL Construction, Inc. for
an additional twenty-nine months in connection with the Pure Water Phase 1 Metropolitan
Biosolids Center Improvements Project.
Subitem-C: 6 votes required pursuant to Charter Section 99.
Committee Actions Taken:
This item was heard at the Environment Committee meeting on January 22, 2026.
ACTION: Motion by Committee Member LaCava, second by Vice Chair Campbell, to
recommend Council approval of staff’s proposed actions.
VOTE: 3-0; Elo-Rivera-yea, Campbell-yea, LaCava-yea.
Engineering & Capital Projects: Elif Cetin, (619) 533-3794
City Attorney Contact: Elizabeth Cason