14. Award of a Construction Contract to Excel Paving Co. for the Construction of the
Bristol Street and Memory Lane Intersection Improvements Project (Project No. 17-
6883) (General & Non-General Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an appropriation adjustment to recognize
$200,000 of spendable fund balance in the Public Works Water Revenue and Water
Utility Capital, Transfer from Fund 060 revenue accounts, and appropriate to the
Water - Interfund Transfer, Transfer to Fund 066 and Water Utility Capital Projects,
Water Capital Project expenditure accounts (Requires five affirmative votes).
2. Approve an amendment to the Fiscal Year 2025-2026 Capital Improvement
Program to include an additional $200,000 in construction funds for the Bristol Street
and Memory Lane Intersection Improvements Project (No. 17-6883).
3. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$2,362,238, which includes $1,889,790 for the construction contract, $283,469 for
contract administration, inspection, and testing, and $188,979 for unanticipated or
unforeseen work.
4. Award a construction contract to Excel Paving Co., the lowest responsible bidder,
in accordance with the base bid in the amount of $1,889,790, subject to change
orders, for construction of the Bristol Street and Memory Lane Intersection
Improvements Project (No. 17-6883), for a term beginning February 17, 2026, and
authorize the City Manager to execute the contract.