Item
10. $1,141,150 CONTRACT WITH WILLIAMS PIPELINE CONTRACTORS, INC FOR
CORONADO AREA WATER MAIN REPLACEMENT
Proposed Motion:
1. Approve Coronado Area Water Main Replacement Project 53032 plans and
specifications.
2. Approve a $1,339,000 Water Fund budget transfer and appropriation from Capital
Improvement Program Project (CIP) 53250 Water Main System Replacement to CIP
Project 53032 Coronado Area Water Main Replacement within the Water Fund (Fund
44).
3. Award $1,141,150 construction contract for Coronado Area Water Main Replacement
Project to Williams Pipeline Contractors, Inc. and authorize City Manager, or designee,
to execute and administer the contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve change orders for
construction and professional engineering construction support services within the