Pasadena
City Council
2. AUTHORIZE THE CITY MANAGER TO ENTER INTO CONTRACTS TO PROVIDE ENGINEERING SERVICES FOR THE POWER PLANT WITH
KEWO
ENGINEERING CORPORATION FOR A GRAND TOTAL NOT-TO-EXCEED AMOUNT OF $1,260,000 AND WORLEY GROUP, INC., FOR A
GRAND TOTAL
NOT-TO-EXCEED AMOUNT OF $1,260,000 FOR UP TO SEVEN YEARS (Water & Power Dept.)
Recommendation: It is recommended that the City Council:
(1) Find that the action proposed in the agenda report is not a “project” subject to the California Environmental Quality Act (“CEQA”) pursuant to
State
CEQA Guidelines Section 21065 and within the meaning of Section 15378(b);
(2) Authorize the City Manager to enter into a contract, as a result of the competitive selection process, as specified by Section 4.08.047 of the
Pasadena
Municipal Code, with Kewo Engineering Corporation (“Kewo”) to provide engineering services for the Power Plant for up to seven years for a grand
total amount
not-to-exceed $1,260,000, which includes the option for two additional one-year extensions or an amount not-to-exceed $360,000, whichever occurs
first, at
the discretion of the City Manager. Competitive price bidding is not required pursuant to City Charter Section 1002(F) Contract for professional or
unique services;
and
(3) Authorize the City Manager to enter into a contract, as a result of the competitive selection process, as specified by Section 4.08.047 of the
Pasadena
Municipal Code, with Worley Group, Inc. (“Worley”) to provide engineering services for the Power Plant for up to seven years for a grand total amount
not-to-exceed $1,260,000, which includes the option for two additional one-year extensions for an amount not-to-exceed $360,000, whichever occurs
first, at
the discretion of the City Manager. Competitive price bidding is not required pursuant to City Charter Section 1002(F) Contract for professional or
unique services.
TPA