Agenda Item
· Fullerton
City Council — Item 10
Original agenda text
Item
10. $1,781,470 CONTRACT WITH NIEVES GENERAL ENGINEERING, INC. FOR
FIRETHORNE AREA STREET REHABILITATION
Proposed Motion:
1. Approve Project 44078 Firethorne Area Street Rehabilitation plans and specifications.
2. Approve the following budget transfers and appropriations in Project 44078 Firethorne
Area Street Rehabilitation:
· $205,000 General Funds (Fund 10) from Project 44589 Residential Street
Program to Project Firethorne Area Street Rehabilitation within the Capital
Projects Fund (Fund 74)
· $1,200,000 Infrastructure Funds (Fund 11) from Project 44400 Street
Reconstruction, Rehabilitation and Repair to Project Firethorne Area Street
Rehabilitation within the Capital Projects Fund (Fund 74)
· $605,000 Measure M2 Funds (Fund 25) from Project 44400 Street Reconstruction,
Rehabilitation and Repair to Project Firethorne Area Street Rehabilitation within
the Capital Projects Fund (Fund 74)
· $60,000 Sewer Enterprise Funds (Fund 47) from Project 51419 Annual Sewer
Replacement Program to Project 44078 Firethorne Area Street Rehabilitation
within the Sewer Enterprise Fund (Fund 47).
3. Award $1,781,470 construction contract to Nieves General Engineering, Inc. for
Firethorne Area Street Rehabilitation Project and authorize City Manager, or
designee, to execute and administer the contract, in a form approved by the City
Attorney.
4. Authorize Director of Public Works, or designee, to approve change orders for
construction and professional engineering construction support services within the
approved project budget.