10. 2025-26 FEDERAL CIRCULATION IMPROVEMENT PROGRAM, PHASE IV,
PROJECT C1018 - PLANS, SPECIFICATIONS, AND CONSTRUCTION
CONTRACTS - This item considers awarding a construction contract for the 2025-26
Federal Circulation Improvement Program, Phase IV project. The improvements will
enhance traffic circulation at the intersection of Valencia Boulevard and McBean
Parkway. Improvements include construction of triple left-turn lanes on eastbound and
westbound Valencia Boulevard, improvements to the existing traffic signal, street
lighting adjustments, hardscape installation, roadway widening, traffic signage and
striping, and landscaping improvements.
RECOMMENDED ACTION:
City Council:
1. Approve the plans and specifications for the 2025-26 Federal Circulation
Improvement Program, Phase IV, Project C1018.
2. Find and determine that the 2025-26 Federal Circulation Improvement Program,
Phase IV project was identified as a traffic mitigation measure (TR-5) and previously
analyzed within the Mitigated Negative Declaration adopted for the Valencia Town
Center by the City of Santa Clarita’s Planning Commission (Resolution P20-01), and
that no further environmental review is required pursuant to the California
Environmental Quality Act Guidelines Section 15162.
3. Award a construction contract to C.A. Rasmussen, Inc., for the 2025-26 Federal
Circulation Improvement Program, Phase IV project in the amount of $2,263,315 and
authorize a contingency in the amount of $339,497, for a total contract amount not to
exceed $2,602,812.
4. Award a professional services contract to Dokken Engineering, to provide
construction support services for the 2025-26 Federal Circulation Improvement
Program, Phase IV project in the amount of $67,920 and authorize a contingency in
the amount of $6,792, for a total contract amount not to exceed $74,712.
5. Award a professional services contract to Allan E. Seward Engineering Geology, Inc.,
for the 2025-26 Federal Circulation Improvement Program, Phase IV project to
provide materials testing and geotechnical inspection services in the amount of
$70,874 and authorize a contingency in the amount of $7,087, for a total contract
amount not to exceed $77,961.
6. Authorize the City Manager or designee to execute all contracts and associated
documents, subject to City Attorney review.