9E. ACCEPTANCE OF CITY OF STANTON COMMUNITY CENTER IMPROVEMENT
PROJECT - BACKUP GENERATOR (TASK CODE NO. 2023-603) BY THE CITY
COUNCIL OF THE CITY OF STANTON, CALIFORNIA
The City of Stanton Community Center Improvement Project - Backup Generator which
consisted of the installation of a backup generator, separately purchased by the City, is
now complete. The final construction cost for the project totaled $338,608.00. The City
Engineer, in his best judgment, certifies that the work was satisfactorily completed as of
April 17, 2026. It is recommended that the City Council accept the completed work
performed on this project.
RECOMMENDED ACTION:
1. City Council declare that this project is categorically exempt under the California
Environmental Quality Act (“CEQA”), Class 1, Section 15301(a) as operation, repair,
and minor interior or exterior alterations of existing public facilities; and
2. Accept the completion of the Stanton Community Center Improvement Project -
Backup Generator, as certified by the City Engineer, and affix the date of completion
of April 17, 2026 as the date of completion of all work associated with this project; and
3. Approve the final cost of construction for the contract amount of $338,608.00 with
Leddy Power Systems, Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to Leddy
Power Systems, Inc. in the amount of $15,678.52.