7. AWARD CONTRACT FOR THE DECONSTRUCTION OF COMMERCE REFUSE-TO-
ENERGY FACILITY (CREA) PROJECT
Staff recommends that the City Council consider adopting a resolution:
1. Finding that Precision Works, Inc. dba Precision Environmental ("Precision
Works") is the lowest responsible and responsive bidder for the Project
pursuant to Public Contract Code 20162, and denies the bid protest
submitted by Resource Environmental, Inc. ("REI"); and
2. Awarding a construction contract to Precision Works, Inc. dba Precision
Environmental as the lowest responsive and responsible bidder for the
Deconstruction of Commerce Refuse-to-Energy Facility (CREA) Project, in the
amount of $1,362,000 for the Total Base Bid Schedule; and
3. Authorizing up to 15% of the construction contract for construction
contingency for unforeseen conditions; and
4. Authorizing up to 10% of the total construction contract and contingencies
for Construction Management and Inspection Services; and
5. Authorizing Construction Management and Inspection Services pursuant to
City's On-Call professional consulting services agreements.