Order of Business 5
c. Glendale Water and Power, re: Amendments to Existing Two Owner’s Engineer (OE)
Professional Services Agreements (PSA) Supporting the Scholl Canyon Biogas
Renewable Generation Project (Scholl Biogas Project)
1. Motion authorizing the City Manager, or his designee, to execute Amendment No. 2 to
the City’s existing PSA, Contract No. 8001327, with TRC Engineers, Inc. (TRC), to
increase the contract amount by $250,000 to a new not-to-exceed amount of
$1,750,000, for continued environmental monitoring and mitigation consulting
services, and extending the PSA Term beyond the currently authorized contract
expiration date of July 28, 2027, and until the final completion of the Scholl Biogas
Project
2. Motion authorizing the City Manager, or his designee, to execute Amendment No. 4 to
the City’s existing PSA, Contract No. 8001391, with Worley Group, Inc. (Worley), to
increase the contract amount by $2,000,000 for a new not-to-exceed amount of
$6,000,000, for continued owner’s engineer’s services, and extending the PSA Term
beyond the currently authorized contract expiration date of September 19, 2027, and
until the final completion of the Scholl Biogas Project