Agenda Item
· Glendale
City Council — Item d
Original agenda text
Order of Business 5
d. Glendale Water and Power, re: Award of contract to Las Colinas Engineering dba
Las Colinas Electrical to Furnish Materials, Equipment, and Labor for the Glendale
Water & Power (GWP) Substation Battery, Charger, and Rack System Replacement
Project
1. Motion authorizing the City Manager, or his designee, to enter into and execute an
Engineering, Procurement and Construction (EPC) contract with Las Colinas
Engineering dba Las Colinas Electrical to furnish materials, equipment, and labor for
GWP’s Substation Battery, Charger, and Rack System Replacement Project (RFP No.
3998), in the amount of $962,961 with a ten percent (10%) contingency of $96,296
2. Resolution of Appropriation