6. NOTICE OF COMPLETION FOR THE MAIN STREET AND 4th STREET SEWER MAIN
REPLACEMENT PROJECT - PHASE 2 - F2M22-53, C2M25-25, M2M26-141
On June 23, 2025, the City Council awarded Contract C2M25-25 to Ramona Inc., for the
Main Street and 4th Street Sewer Main Replacement Project - Phase 2 in an amount not
to exceed $2,941,665.50.
There were two authorized change orders during the project. These change orders
involved grinding and paving Main Street from Atlantic Boulevard to 4th Street, as well as
various miscellaneous items that were unforeseen during construction. The change orders
increased the total amount of the contract by $201,729.99, for a total project cost of
$3,143,395.49.
The project has been completed in accordance with the City’s requirements and
specifications. As such, it would be appropriate for the City Council to accept the project
as complete and instruct the City Clerk that the Notice of Completion be filed with the
County of Los Angeles Recorder’s Office
Recommended Action: City Council accept the work of Ramona Inc., for the Main
Street and 4th Street Sewer Main Replacement Project - Phase 2 in the amount of
$3,143,395.49, as complete; direct the City Clerk to file a Notice of Completion with the
County of Los Angeles for recordation; release the five percent retention 35 days from the
date of recordation if no liens are filed; and direct staff to undertake the steps necessary
to finalize Council’s action (M2M26-141)