20. 26-728 Accept Lowest Responsive and Responsible Bid and Award a
Construction Contract to Newbuild Construction and Restoration,
Inc. in the amount of $628,600 for the Newland House Museum &
Water Tower Restoration, CC1788
Recommended Action:
A) Authorize the appropriation of $101,385.40 from the Infrastructure Fund (314) balance
to Account 31440023.82200; and,
B) Accept the lowest responsive and responsible bid submitted by Newbuild Construction
and Restoration, Inc. in the amount of $589,600 and the optional additive costs associated
with painting the Newland Barn in the amount of $39,000 for a total bid price of $628,600;
and,
C) Authorize the Director of Public Works to approve construction change orders within
the approved contingency amount of twenty percent (5%) of the contract amount; and,
D) Authorize the Mayor and City Clerk to execute a construction contract in a form
approved by the City Attorney.