Order of Business 1
1.eAPPROVAL OF PLANS AND AWARD OF CONSTRUCTION CONTRACT TO KALBAN, INC. FOR THE CDBG SIDEWALK AND CURB RAMP ADA IMPROVEMENT PROJECT, CITY PROJECT NO. 27-101
Fiscal Impact:
Expense: $214,125.56 Total Construction Cost
$155,000.00 Construction Contract Amount
$ 15,500.00 Construction Contingency Amount
$ 43,625.56 Construction Inspection and Management Costs
Available Budget: $214,125.56 Total Project Budget City Project No. 27-101
$176,679.00
Fiscal Year 2026-27 CIP Budget - CDBG
(204-80100-9600)
$ 37,446.56 Measure U (102-80100-9600)
Recommended Action: It is recommended that the City Council:
Approve the Engineered Plans and Specifications prepared by the Engineering Department for the CDBG Sidewalk and Curb Ramp ADA Improvement Project, City Project No. 27-101; and
Approve a Public Works Agreement with Kalban, Inc., for the CDBG Sidewalk and Curb Ramp ADA Improvement Project in the amount of $155,000.00; and
Reject all other bids received and authorize return of the bid bonds; and
Authorize the Acting City Administrator to approve contract change orders up to ten percent (10%) of the contract amount, or $15,500.00, for a total construction contract not-to-exceed amount of $170,500; and
Approve a purchase order with Berg and Associates to provide construction management and inspection services for a not-to-exceed amount of $43,625.56; and
Authorize the Acting City Administrator and/or her designee to execute all necessary documents, in a form approved by the City Attorney.