Order of Business 1
1.dAMENDMENT NO. 1 TO THE PUBLIC WORKS AGREEMENT WITH CT&T CONCRETE PAVING FOR CONSTRUCTION SERVICES RELATED TO THE GOLDEN AVENUE BRIDGE REPLACEMENT PROJECT
Fiscal Impact:
Additional Expense: $ 111,298.95 Construction Cost
Available Budget: $6,875,873.55 Total Project Budget
$2,200,000.00
Community Project Funding/Congressionally
Directed Spending (CPFCDS)
(505-90300-9600)
$2,647,046.00
Highway Bridge Program (HBP)
(224-90400-9600)
$ 215,682.00
County of Orange OC Loop Segment D
Contribution
$1,313,145.55
Measure U (including required City Federal
Match) (102-90300-9600)
$ 500,000.00 Brandywine Developer Agreement Contribution
Recommended Action: It is recommended that the City Council:
Approve Amendment No. 1 to a Public Works Agreement with CT&T Concrete Paving for an additional $528,505.87, for an updated contract amount of $5,215,516.37; and
Authorize the Acting City Administrator or her designee to approve contract change orders up to 10%, or $51,494.13, of the Amendment amount for a not-to-exceed amount of $5,267,010.50; and
Authorize the Acting City Administrator and/or her designee to execute the necessary documents, in a form approved by the City Attorney.