Agenda Item
· Santa Fe Springs
City Council — Item 16
Original agenda text
Item
16. AQUATIC CENTER IMPROVEMENT PROJECT (PHASE 1B) - PROJECT CLOSEOUT, FINAL COST
RECONCILIATION, AND ADDITIONAL APPROPRIATION OF FUNDS (PUBLIC WORKS)
It is recommended that the City Council:
1. Approve the final payment to PCN3, Inc. in the amount of $283,349.44 (Less 5% Retention); and
2. Approve the final construction contract amount with PCN3, Inc. in the amount of $10,644,206.63,
including Contract Change Order Nos. 1 through 9 in the aggregate amount of $1,138,206.63
(Attachment A); and
3. Appropriate $350,000 from the CIP Reserve to the Project Account No. PW220014 to cover the
projected funding shortfall and close out the project; and
4. Authorize the Director of Public Works to file the Notice of Completion with the Los Angeles County
Registrar-Recorder; and
5. Take such additional, related action that may be desirable.