Costa Mesa
City Council
1. AWARD OF THE FIRE STATION NO. 2 RECONSTRUCTION 26-453
PROJECT, CITY PROJECT NO. 26-05
RECOMMENDATION:
Staff recommends the City Council:
1. Adopt plans, specifications, and working details for the Fire Station No. 2
Reconstruction Project, City Project No. 26-05.
2. Authorize the City Attorney to prepare and the City Manager and City Clerk
to execute a Public Works Agreement (PWA) for construction with AMG &
Associates, Inc., 26535 Summit Circle, Santa Clarita, CA 91350, in the
amount of $14,821,000, plus a ten percent (10%) contingency for the PWA in
the amount of $1,482,100, contingent upon the approval and completion of
bond financing.
3. Approve Amendment No.1 to the Professional Services Agreement (PSA)
with PBK-WLC Architects for professional architectural and engineering
support services, extending the term of the agreement for a period of three
(3) years through February of 2030.
4. Approve Amendment No. 2 to the Professional Services Agreement (PSA)
with TSG Enterprises, Inc. dba The Solis Group for the administration of
Community Workforce Agreement (CWA), extending the term of the
agreement for a period of two (2) years through April of 2030.
5. Authorize the City Manager or designee and City Clerk to execute the
agreements, amendments, and any future amendments to the agreements,
including increases to the not-to-exceed amount within City Council authority.
ENVIRONMENTAL DETERMINATION:
The project was presented to the Planning Commission on October 14, 2024, for
environmental and Minor Conditional Use Permit (CUP) approvals. The project
was determined to be categorically exempt from the provisions of the California
Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15302
(Class 2), Replacement or Reconstruction. Under Class 2, a project consisting of
the replacement or reconstruction of existing structures and facilities where the
new structure will be located on the same site as the structure replaced and will
have substantially the same purpose and capacity as the structure replaced is
eligible for the exemption. Since the project is replacing the existing fire station
with a new fire station with the same purpose and substantially the same
capacity, the proposed development project meets all criteria for a Class 2
Categorical Exemption pursuant to CEQA Guidelines Section 15302.
Attachments: 1. Bid Results
2. Denial Letter for PCN3, Inc.
3. Denial Letter for Builders United, LLC
ADDITIONAL COUNCIL/BOARD MEMBER COMMITTEE REPORTS, COMMENTS, AND