South El Monte
City Council
9.a. AN INTERIM URGENCY ORDINANCE OF THE CITY OF SOUTH EL
MONTE, CALIFORNIA, CONTINUING A TEMPORARY CITYWIDE
MORATORIUM PROHIBITING APPROVAL AND ACCEPTANCE OF
NEW DATA CENTER LAND USE APPLICATIONS FOR AN
ADDITIONAL TEN (10) MONTHS AND FIFTEEN (15) DAYS PURSUANT
TO GOVERNMENT CODE SECTION 65858
The proposed interim urgency ordinance would extend the existing 45-day
moratorium on the approval and acceptance of new Data Center land use
applications for an additional ten (10) months and fifteen (15) days while
the City continues to evaluate appropriate land use classifications, zoning
regulations, and development standards. The extension would provide
additional time for the City to address potential impacts associated with
Data Center development, including intensive energy and water demands,
infrastructure capacity limitations, noise, air quality, and public health and
safety concerns.
RECOMMENDED ACTION: Staff recommends the City Council:
1. Determine that Urgency Ordinance No. 1301-U is categorically
exempt from the California Environmental Quality Act (CEQA)
pursuant to State CEQA Guidelines Section 15061 (b)(3) (Common
Sense Exemption); and
2. Introduce by title only, and waive further reading of, Urgency
Ordinance No. 1301-U extending Interim Urgency Ordinance No.
1299-U and the temporary citywide moratorium on the approval and
acceptance of new Data Center land use applications for an
additional ten (10) months and fifteen (15) days.