Order of Business 9
9L. ACCEPTANCE OF THE FY 26/27 CITYWIDE SIDEWALK REPAIR PROJECT (TASK
CODE NO. 2027-103) BY THE CITY COUNCIL OF THE CITY OF STANTON,
CALIFORNIA
The FY 26/27 Citywide Sidewalk Repair Project, consisting of the removal and
replacement of concrete sidewalks, curbs and gutters, along with all appurtenant work is
now complete. The final construction cost for the project was $72,375.00. The City
Engineer, in his judgment, certifies that the work was satisfactorily completed as of
October 13, 2026, and recommends that the City Council accept the completed work
performed on this project.
RECOMMENDED ACTION:
1. City Council find that this project is exempt from the California Environmental Quality
Act (“CEQA”), Class 1, and Section 15301(c) as repair, maintenance, and minor
alteration of existing streets, sidewalks, gutters, and similar facilities; and
2. Accept the completion of improvements for the FY 26/27 Citywide Sidewalk Repair
Project, as certified by the City Engineer, and affix the date of October 13, 2026, as
the date of completion of all work on this project; and
3. Approve the final construction contract amount of $72,375.00 with CJ Concrete
Construction, Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment A) with the County Clerk-Recorder of the County of
Orange; and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to CJ
Concrete Construction, Inc. in the amount of $3,618.75.