Lancaster
City Council
CC 5. Acceptance of Public Works Construction Project No. 22-007 -2024 Safer Streets Action
Plan
Accept the work constructed by PS Development Corporation, DBA Comet Electric of
Chatsworth, California, for Public Works Construction Project (PWCP) No. 22-007, 2024
Safer Streets Action Plan, and direct the City Clerk to file the Notice of Completion for the
project. Retention on this project shall be administered in accordance with California Public
Contract Code Section 22038(b).
Construction of the project has been completed to the satisfaction of the Director of Public
Works. The project was substantially completed on April 03, 2026, which was within the time
permitted by the contract. The construction quantities and the amount of payment have been
approved by the Contractor and Director of Public Works.