15. $2,389,800 CONTRACT WITH WILLIAMS PIPELINE CONTRACTORS, INC. FOR
THE ASH-WOODS AREA INFRASTRUCTURE IMPROVEMENTS PROJECT
Proposed Motion:
1. Approve the Ash-Woods Area Infrastructure Improvements Project plans and
specifications.
2. Approve the following budget transfers and appropriations in Project 53061
Ash-Woods Area Infrastructure Improvements Project:
· $2,180,500 Water Fund (Fund 44) transfer and appropriation from Project 53250
Water Main System Replacement to Project 53061 Ash-Woods Area Infrastructure
Improvements Project within the Water Fund (Fund 44)
· $659,500 Sewer Enterprise Funds (Fund 47) transfer and appropriation from
Project 51419 Annual Sewer Replacement Program to Project 53061 Ash-Woods
Area Infrastructure Improvements Project within the Sewer Enterprise Fund (Fund
47).
3. Award $2,389,800 construction contract for the Ash-Woods Area Infrastructure
Improvements Project to Williams Pipeline Contractors, Inc. and authorize City
Manager, or designee, to execute and administer the contract, in a form approved by
the City Attorney.
4. Authorize Public Works Director, or designee, to approve change orders for
construction and professional engineering construction support services within the