Agenda Item
· Los Angeles
LA County Board — Item 8
Original agenda text
Item
8. Phased Redevelopment of the Los Angeles County General Hospital and
West Campus Master Option Agreement
Recommendation: Find that the recommended actions either do not constitute a
project under the California Environmental Quality Act (CEQA) or are within the
scope of the project impacts analyzed in the County’s certified Subsequent
Environmental Impact Report (SEIR) for the previously approved Los Angeles
County General Hospital Campus Master Plan (Master Plan); authorize the
Director of Economic Opportunity (DEO) to make findings in connection with
the delegated actions herein that the actions are within the scope of the SEIR, if
appropriate, and that pursuant to State CEQA Guidelines Sections 15162 and
15168, no new environmental document is required, that the Board's previously
approved Findings of Fact, Statement of Overriding Considerations and
Mitigation Monitoring and Reporting Program continue to apply to delegated
actions proposed for approval, and to file Notices of Determination, as
appropriate, in connection with such approvals. Adopt an enabling ordinance
authorizing the ground lease agreements between the County and Centennial
Partners pursuant to Government Code section 25515 et seq. Find the
following: the proposed ground leases will result in economic benefits to the
County; the public benefit of the proposed lease agreements is expected to be
greater than the public benefit which would result from the sale of the property;
a reasonable expectation exists that future public need justifies retention of the
fee ownership of the property; and the proposed leases will not interfere with
the use or development of the remaining public property. Authorize the Director
to take the following actions: (Supervisorial District 1) (Department of
Economic Opportunity) ADOPT 4-VOTES (Relates to Agenda No. 12)
Negotiate and execute a Master Option Agreement (MOA) with
Centennial Partners (Developer), in a form substantially consistent with
the development framework and general conditions described herein, for
the proposed phased redevelopment of approximately 30.8 acres of the
Los Angeles County General Hospital and West Campus (Campus),
provided that the MOA is executed no later than June 30, 2027, or such
later date to which the term of the Exclusive Negotiating Agreement
(ENA) with the Developer may be extended and the material terms of the
MOA remain consistent with the authority granted by the Board herein;
and to execute any amendments to the MOA that are consistent with such
authority.
Oversee the proposed phased build-out of the Campus and ensure that
development proceeds in accordance with the Master Plan and Use &
Development Standards, adopted by the Board on October 20, 2026; the
SEIR, certified by the Board on October 20, 2026, such that development
is determined by DEO to be within the scope of the impacts analyzed in
the SEIR; the Option Release Process, to be memorialized in the MOA;
and the Community Benefits Agreement Framework, executed between
the Developer and The Los Angeles General Medical Center Foundation,
Inc. on behalf of the Health Innovation Community Partnership, attached
hereto, which the County will enforce as a third party beneficiary
(collectively, the Governing Framework), such that, at full build-out as
proposed, the Campus is a mixed-use “Healthy Village” in which the total
development for each land use is within the range shown in the
development program described herein.
Approve Project Proposals submitted under the MOA for Phase-specific
development (each, a Phase Plan), and negotiate and execute future
proposed Project Option Agreements with Developer, or DEO-approved
assignee, for each such Phase Plan (each, a Phase Plan Option),
provided that each Phase Plan and Phase Plan Option is substantially
consistent with the Governing Framework and that the Developer and its
affiliates are not then in an uncured material default under the MOA, any
proposed Phase Plan Option, or any previously executed ground lease
on the Campus.
Negotiate and execute one or more ground leases with Developer, or
DEO-approved assignee, for Category 1 Projects and Category 2
Projects (each as defined in the MOA and described below) following
exercise of the applicable Phase Plan Option to draw down a ground
lease and satisfaction of the conditions established in the applicable
Phase Plan Option for the applicable development site, provided that the
proposed ground lease and proposed development of the applicable
Phase Plan remain consistent with the authority granted herein.
Execute amendments and ancillary documentation necessary to
effectuate the MOA, applicable Phase Plan Option, or ground leases,
provided that such actions are consistent with the terms and limitations
authorized by the Board herein and do not otherwise require further
Board approval.
Amend the Campus Stabilization Disbursement Agreement in an amount
not to exceed $665,000 from the Los Angeles County Department of
Health Services Fund Balance for the development of a Concept and
Schematic Design for a proposed new facility to replace the existing
Supply Chain Warehouse. (26-6819)
Community Services