21. 24-232 Accept bid and authorize execution of a construction contract with\nKlassic Engineering & Construction, Inc. in the amount of\n$273,425.90 for the LeBard Park Improvements Project,\nCC-1668 and authorize change orders not to exceed 15 percent\nRecommended Action:\nA) Accept the next lowest responsive and responsible bid submitted by Klassic\nEngineering & Construction, Inc. in the amended amount of $273,425.90; and,\nB) Authorize the Mayor and City Clerk to execute a construction contract in the form\napproved by the City Attorney; and,\nC) Authorize the Director of Public Works to execute change orders not to exceed a total\nof 15 percent of the contract construction costs, or $41,013.89 .