16) Award of a Public Works Construction Agreement to Aneen Construction, Inc.\nfor the Avenues Master Plan Storm Drain Improvement Project Z10032\n1. Approve and authorize the City Manager to execute the Agreement with Aneen\nConstruction Inc. for the Avenues Master Plan Storm Drain Improvement Project in\nan amount not to exceed $2,257,882.50 as approved by the City Attorney and\nexecute change orders not to exceed a 10% contingency amount of $225,788.00;\nand\nCity of Lake Elsinore Page 6\nCity Council Agenda - Final May 14, 2024\n2. Authorize the City Clerk to record the Notice of Completion once it is determined\nthe work is complete and the improvements are accepted into the City maintained\ndrainage network.