Apple Valley
City Council
Agenda Item 8
6.8 ACCEPTANCE OF WORK FOR THE CHIP SEAL 2024 PROJECT\nThat the Town Council:\nA. Accept the work completed by American Pavement Systems, Inc. for the Chip Seal 2024 project for a total contract cost\nof $2,217,506.20.\nB. Direct the Town Clerk to file the Notice of Completion for the contract work.\nC. Direct the Finance Director to release the retained funds 30 days after the Notice of Completion has been filed, provided\nno claims are filed against the contractor.