Cudahy

City Council

December 03, 2024 Order of Business 12 #B

Agenda Item B

B. Consideration to Approve Construction Contingency and Contract Change Order to the Contract\nServices Agreement with Elecnor-Belco Electric, for the Salt Lake Avenue Pedestrian Safety\nImprovement Project – CIP Project No. TRE-001 (page 27)\nPresented by the Public Works Director\nRecommendation: The City Council is requested to approve 10% Construction Contingency\nin the amount of $20,018 and Contract Change Order (CCO) No. 1 in the\namount of $28,000 to the existing Contract Services Agreement in the\namount of $200,182 with Elecnor-Belco Electric, Inc., for the Salt Lake\nAvenue Pedestrian Safety Improvement Project, City Project No. TRE-001,\nfunded by the Highway Safety Improvement Grant Program Cycle 7\n(HSIP-7).