January 14, 2025 Order of Business 1 #g

Agenda Item g

1.g Award of Contract to CJ Concrete Construction, Inc. for FY 2024-25 Concrete Repair\nProject, City Project No. 1502\nFiscal Impact:\nExpense: $ 110,246.40 Total Construction Contract Amount\n$ 91,872.00 Construction Contract Amount\n$ 18,374.40 Construction Contingency Amount\nAvailable Budget: $ 140,780.00 Fiscal Year 2024-25 CIP Budget\n(791502-6740)\nRecommended Action: It is recommended the City Council:\n1. Award a Public Works Agreement to CJ Concrete Construction, Inc., for the FY 2024-\n25 Concrete Repair Project, City Project No. 1502, in the amount of $91,872; and\n2. Reject all other bids received and authorize the return of the bid bonds; and\n3. Authorize the Interim City Administrator to approve contract change orders up to 20%\nor $18,374.40 for a total construction contract not-to-exceed amount of $110,246.40;\nand\n4. Authorize the Interim City Administrator and/or his designee to execute all necessary\ndocuments, in a form approved by the City Attorney.