1. Pressure Zone Change Project - Area 7 District – Approve Notice of Exemption and\nAward of Construction Contract\nRecommendation:\nThat the Honorable Board of Directors:\n(1) Open and conduct a Public Hearing, receiving testimony regarding the proposed\ncapital improvement project (CIP);\n(2) Close the Public Hearing;\n(3) Find the project exempt from environmental review under the California\nEnvironmental Quality Act (CEQA) pursuant to Section 15301(b) of the CEQA\nguidelines and Approve the Notice of Exemption; and\n(4) Award a construction contract to Hemet Manufacturing Company, Inc., DBA\nGenesis Construction in the amount of $2,011,621.00, for the Pressure Zone\nChange Project – Area 7 District Project No. CC25-027.