Laguna Niguel

City Council

May 06, 2025 Consent Item #8

Agenda Item 8

8. Award of Construction Contract to All American Asphalt for the Residential\nAnnual Resurfacing Program Zones V & VI – Phase 2, Cash Contract No. 24-\n07\nRecommendation\nStaff recommends that the City Council:\n1. Award of Construction Contract to All American Asphalt for the Residential\nAnnual Resurfacing Program Zones V & VI – Phase 2, Cash Contract No.\n24-07 in the amount of $2,839,500;\n2. Authorize the Public Works Director/City Engineer to process change\norders in an amount not to exceed 20% of the contract for $567,900, for a\ntotal not-to-exceed amount of $3,407,400 if needed;\n3. Authorize the City Manager to execute the Construction Contract for the\nResidential Annual Resurfacing Program Zones V & VI – Phase 2, Cash\nContract No. 24-07 to All American Asphalt, subject to the City Attorney\nmaking non-substantive changes; and,\n4. Authorize the Public Works Director/City Engineer to execute the Notice of\nCompletion at the conclusion of construction.